…Officer and DEP Commissioner Rohit T. Aggarwala. “This is one of our most ambitious green infrastructure projects to date, complementing the many other innovative initiatives we are already utilizing – including the recently expanded Cloudburst Program, Bluebelts, rain gardens and green roofs – to tackle climate change.” The daylighting project will remove four to five million gallons of water from the sewer system each day, more on rainy days…. final component, the city will now move forward with rerouting the brook above ground, an engineering feat known as ‘daylighting,’ and will complete one of the most ambitious green infrastructure projects to date. Construction is expected to begin in 2025 and the overall daylighting and greenway project budget is $133 million. Removing…

newyorkconstructionreport.com

Total Engagement: 0 ?Green Roofs, Green Infass Alerts Read More